Installation:
Cooling Tunnels &
Process Area AC,
Bendigo 2007
3 x Cooling Tunnels-175kWR tot
900kg/h of Pita bread out of oven entering tunnel
at 90°C → 20°C leaving tunnel in 3min retention
time.
7 x 5FANØ330 Lu-Ve Low Profile Dual Discharge Evaporators
2 x 4FANØ630 Lu-Ve Axial Air Cooled Condensers
1 x ENVIRO HGX8/2470
A fully wired compressor package, which utilises a single
Bock 8cyl semi-hermetic compressor with step capacity control
for effective operation to any load condition.
3 x Carel Master-Cellar Digital Thermostat Room Controls
All tunnels are running very well and above expectation!
Considering this is our first installation of this type
we are proud to say that it has been a great success and
look forward to similar projects in the future.
Process Area AC-120kWR tot
2 x Temperzone 3PH Reverse Cycle Ducted Split Systems
2 x 18m Lengths Ø710 Fabric Duct Socks producing
3000L/s ea
RBR managed all areas of the project. This included shed
& freezer room construction, all concrete works including
loading ramp, electrical wiring & floor heating and
also the installation of a Tieman dock leveler.
However our primarily role involved the design, manufacture,
installation and commissioning of a refrigeration plant
to achieve the below load conditions.
15 Ton Pastries/Corn-chips entering @ 40°C → -18°C
leaving frozen in a freeze period of 48hrs
Freezer Room-140kWR tot
2 x 4FANØ630 Lu-Ve Industrial Evaporators
1 x 8FAN Buffalo Split Circuit Air Cooled Condenser
2 x Fully wired Bitzer semi-hermetic screw compressor packages,
complete with oil cooling and sub cooling to 2°C
Innotech/Carel Control System with dialup facility for remote
access
System was intelligently designed to enable dual redundancy
in the unlikely event of a failure.
Click on pictures to enlarge
|
 |
|
|
|
Existing Conveyer System; Pita Bread
at 90°C |
Installation of Cooling Tunnels |
|
|
|
Pita Bread out of tunnel at 20°C in 3mins
|
RBR Compressor Package & Lu-Ve
Condenser |
|
|
|
|
Lu-Ve Condenser mounted on stand |
Rositas Freezer Complex |
|
|
|
|
Screw Compressor Packages & Split Circuit Condenser |
Loading Ramp with Tieman Dock Leveller |
|
|
|
|